City of Wenatchee moratorium
City of Wenatchee, Washington paused new data center approvals on 22 Feb 2018 for 6 months, citing zoning and rules and infrastructure. The pause has ended. It covers 4 tracked campuses. Checked 23 Nov 2026
Started 22 Feb 2018EndedEnded 21 Aug 2018
The facts
- Applies to
- Not quantified in primary city code table; regional reports describe delayed or redirected bitcoin data center investment, including a $100 million Salcido Enterprises expansion that was redirected outside Washington (NWPB, 2018-04-09)
- Reason
- Cryptocurrency mining/high-density-load growth, power-distribution concerns, and fire/safety concerns identified during the Chelan PUD-driven regional response
- Term
- Initial six-month interim official control under RCW 35A.63.220 and RCW 36.70A.390; extended for an additional six months by Ordinance 2019-04 (effective approximately 2019-02-23) until permanent zoning amendments were adopted
- Legal basis
- Ordinance 2018-04 (interim official control, "Not codified" per Wenatchee ordinance table); Ordinance 2019-04 (extension; repealed by Ordinance 2019-30); Ordinance 2019-30 (permanent regulations); RCW 35A.63.220 and RCW 36.70A.390
- What happened next
- Ordinance 2019-30 added WMC 10.48.310, amended sections 10.08.050, 10.08.055, and 10.10.020 to regulate cryptocurrency mining and data centers, and repealed Ordinance 2019-04
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when City of Wenatchee votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (4 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.