Town of Hildebran moratorium
Town of Hildebran, North Carolina paused new data center approvals on 24 Aug 2026, citing specific project and grid and power. It covers 1 tracked campus. Checked 23 Nov 2026
In force since 24 Aug 2026No end date on record
The facts
- Applies to
- DigiPower X AI data center campus proposal (~150 MW).
- Term
- 12 months (to about 2027-08-24)
- What happened next
- 12-month moratorium adopted despite earlier zoning rules.
- Reason
- DigiPower X plans an AI data center campus (about 75 MW in 2029 and 75 MW in 2030) on ~40 acres near a switchyard; residents petitioned for a pause
- Legal basis
- Town of Hildebran data center moratorium (number not located); adopted after the town's March 2026 permanent data center zoning regulations
Campuses in reach
Apple Inc.Catawba CountySite permit·≈62–290 MWBoyd Farms Data CenterCatawba CountySite permit·MicrosoftCLT40 Data CenterCatawba CountySite permit·≈7–33 MWLyle Creek Data CenterCatawba CountySite permit·MicrosoftStover North Data CenterCatawba CountySite permit·MicrosoftCompass Datacenters Statesville CampusIredell CountySite permit·Compass
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Town of Hildebran votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.