In forceMoratorium

East Lansing moratorium

East Lansing, Michigan paused new data center approvals on 17 Mar 2026, citing zoning and rules and noise. It covers 1 tracked campus. Checked 23 Nov 2026

In force since 17 Mar 2026No end date on record

The facts

Passed by
City Council, 17 Mar 2026
Applies to
None; several informal inquiries but no applications
Legal basis
City Council Policy Resolution 2026-8 and extension Policy Resolution 2026-45
Reason
Zoning ordinance does not address data centers; staff workgroup drafting regulations (noise, water, wellhead protection, energy)
Term
Six calendar months under PR2026-8, extended by six calendar months under PR2026-45; exact extension endpoint and operative interval unresolved.
What happened next
Internal workgroup developing ordinance language for Planning Commission and Council
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when East Lansing votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near East Lansing paused data centers?