Lansing moratorium
Lansing, Michigan paused new data center approvals on 13 Jul 2026 for 6 months, citing zoning and rules. It covers 10 tracked campuses. Checked 23 Nov 2026
Started 13 Jul 20264 of 6 months passedEnds 11 Jan 2027
The facts
- Legal basis
- Lansing Ordinance No. 1359, adding Chapter 878 of the city code
- Reason
- Bars issuance of building permits for data centers and processing of zoning amendment applications that would permit a data center as a principal or accessory use
- Term
- 182 days from the effective date; City Clerk summary states July 28, 2026 effectiveness. Exact endpoint convention and later actions unresolved.
- What happened next
- City Council voted 7-1 to add Chapter 878, a 182-day moratorium on data center building permits and enabling zoning amendments
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Lansing votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (10 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.