Elkhart moratorium

Elkhart, Indiana paused new data center approvals on 27 Aug 2026, citing zoning and rules and grid and power. It covers 1 tracked campus. Checked 23 Nov 2026

In force since 27 Aug 2026No end date on record

The facts

Reason
Council sought time to develop city standards addressing electrical grid capacity, water and air impacts, sound, and setbacks before accepting new hyperscale data center and BESS applications
Term
Through December 31, 2027, or until the city adopts data center/BESS development standards
Legal basis
Elkhart Common Council ordinance, adopted 9-0 at a special meeting on 2026-08-27, pausing acceptance of new data center and battery energy storage system (BESS) applications
What happened next
Common Council adopted a moratorium on data center and battery storage facility applications through Dec. 31, 2027

Know when Elkhart votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Elkhart paused data centers?