Frenchtown Charter Township (Monroe County) moratorium
Frenchtown Charter Township (Monroe County), Michigan paused new data center approvals on 28 Apr 2026, citing specific project and grid and power. Checked 23 Nov 2026
In force since 28 Apr 2026No end date on record
The facts
- What happened next
- Township drafting data center ordinance
- Applies to
- Data center interest in the township (1500 N. Dixie Hwy former golf course property raised by residents); no application pending per planning consultant
- Reason
- Data center proposed in the township (golf course property at 1500 N. Dixie Hwy discussed); concern over electricity, water and natural-resource demand
- Term
- Original term previously reported as six months; executed Ordinance 300-19 and its precise operative anchor remain unverified. The October 13 extension is documented separately in current_status.
- Legal basis
- Zoning Ordinance No. 300-19, interim/temporary zoning ordinance amendment establishing a temporary moratorium as to Technology Uses, Data Center Uses and Other High Resource Demand Uses (adopted 2026-04-28), under Zoning Ordinance No. 300 Section 7.13 and the Board's 2026-03-10 resolution
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Frenchtown Charter Township (Monroe County) votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.