LaGrange moratorium
LaGrange, Georgia paused new data center approvals on 23 Sep 2025 for 6 months, citing zoning and rules and noise. The pause has ended. It covers 7 tracked campuses. Checked 23 Nov 2026
Started 23 Sep 2025EndedEnded 22 Mar 2026
The facts
- Passed by
- City Council, 23 Sep 2025
- Applies to
- Existing Pegasus Parkway project excluded
- Reason
- Need to review zoning, noise, and property-impact rules
- What happened next
- Staff-directed code review
- Term
- Original 180 days from 2025-09-23. On 2026-02-24 the City Council unanimously authorized the Mayor and City Clerk to sign an extension through 2026-05-12; the signed extension and operative transition to later zoning are unverified.
- Legal basis
- LaGrange City Council 180-day moratorium reported adopted 2025-09-23; official February 24, 2026 minutes record unanimous authorization to sign an extension through May 12. April 18 reporting describes a 3-2 council vote on the preceding Tuesday, April 14, to approve a substitute special-use-permit ordinance for data centers in industrial zoning. The signed extension and operative transition remain unverified.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when LaGrange votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (7 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.