EndedMoratorium

Troup County moratorium

Troup County, Georgia paused new data center approvals on 16 Sep 2025 for 3 months, citing specific project and infrastructure. The pause has ended. It covers 5 tracked campuses. Checked 23 Nov 2026

Started 16 Sep 2025EndedEnded 15 Dec 2025

The facts

Applies to
Project West, reported about $9.7 billion, 513 acres, and nearly 600 MW
Reason
Project West and broader power, water, and land-use concerns
Term
90 days from 2025-09-16, extended 90 days on 2025-12-02 (to 2026-03-16), and extended a further 90 days on 2026-02-17 (to 2026-06-14), per the county's official public notice.
Legal basis
Troup County 90-day moratorium with public notice for extension (per Ledger-Enquirer reporting cited in GPB 2025-10-22)
What happened next
The Board of Commissioners approved data-center zoning rules and lifted the moratorium in May 2026, according to LaGrange Daily News.

Know when Troup County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (5 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Troup County paused data centers?