In forceMoratorium

Monroeville moratorium

Monroeville, Ohio paused new data center approvals on 24 Feb 2026, citing specific project and grid and power. It covers 1 tracked campus. Checked 23 Nov 2026

In force since 24 Feb 2026No end date on record

The facts

Term
Twelve (12) months from the effective date (emergency, effective immediately)
Applies to
Decimal Digital proposed AI data center on ~50 acres in the Fort Monroe Industrial Park. The existing Gray Matter-related Bitcoin mining site at 17 Fort Monroe Industrial Parkway is in receivership.
Reason
Roughly $1.3M in unpaid electric bills from the Gray Matter cryptocurrency mining operation in the Fort Monroe industrial park (now in receivership), plus Decimal Digital's purchase of ~50 acres for a proposed AI data center. Concerns about electric rates, water, noise.
Legal basis
Village of Monroeville Resolution 2026-01; amended by Resolution 2026-02 adopted March 10, 2026, to include cryptocurrency mining centers
What happened next
Review of federal/state codes and village ordinances; council work sessions on zoning (overlay district or conditional use), FAQ, possible advisory ballot.
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Monroeville votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Monroeville paused data centers?