Wellington moratorium
Wellington, Ohio paused new data center approvals on 16 Mar 2026, citing zoning and rules and land use. Checked 23 Nov 2026
In force since 16 Mar 2026No end date on record
The facts
- Applies to
- None named.
- Term
- One year, with an option to extend for one additional year.
- Reason
- Preemptive; prompted by data center and mega-site controversies in nearby Lorain County communities (New Russia Township mega site, Brownhelm Township land purchases); no Wellington project proposed.
- Legal basis
- Ordinance 2026-07 (Village of Wellington), temporarily halting issuance of zoning certificates for data processing and hosting facilities
- What happened next
- Village council adopted a one-year pause on zoning certificates for data centers to review regulations and decide how such uses might fit the village.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Wellington votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.