In forceMoratorium

Otsego moratorium

Otsego, Minnesota paused new data center approvals on 27 Jul 2026, citing zoning and rules and land use. Checked 23 Nov 2026

In force since 27 Jul 2026No end date on record

The facts

Passed by
Otsego City Council, 27 Jul 2026
Applies to
None; the City has not received any data center site-plan application as of the July 27, 2026 adoption, per City Planner Dan Licht.
Reason
City has not received any data center site-plan applications but sought to study the use pre-emptively; Planning Commission found the existing Zoning Ordinance (which permits data centers in the B-4, I-1, and I-2 districts) may be inadequate given the changing nature of such uses
Term
Up to one year; at adoption the planner described earlier expiration after the study and an adopted ordinance. Unsigned agenda text provides one year from effectiveness upon passage and publication, with earlier repeal or an effective zoning amendment; final text and publication date remain unverified.
Legal basis
Ordinance 2026-11, an interim ordinance imposing a moratorium and authorizing a study of official controls for data centers, adopted 5-0 by the Otsego City Council on July 27, 2026 under Minn. Stat. Sec. 462.355, subd. 4; recommended 7-0 by the Planning Commission at its July 6, 2026 special meeting.
What happened next
Adopted: the Otsego City Council voted 5-0 on July 27, 2026 to adopt Ordinance 2026-11, imposing a one-year moratorium on data center land uses and directing staff to study official controls and impacts (water, noise, setbacks, lighting, safety) before drafting permanent zoning regulations.

Know when Otsego votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Otsego paused data centers?