Wright County moratorium
Wright County, Minnesota paused new data center approvals on 19 May 2026, citing zoning and rules and infrastructure. It covers 3 tracked campuses. Checked 23 Nov 2026
In force since 19 May 2026No end date on record
The facts
- Passed by
- Wright County Board of Commissioners, 19 May 2026
- Applies to
- Not specified in the ordinance
- Term
- One year from the effective date, unless earlier terminated by the County Board
- Reason
- County Office of Planning and Zoning began receiving data center development inquiries and permit pressure; County Zoning Ordinance does not expressly regulate data centers
- Legal basis
- Interim Ordinance No. 26-2, 'Resolution Adopting an Interim Zoning Ordinance Instituting an Emergency Moratorium on Data Centers,' adopted by the Wright County Board of Commissioners May 19, 2026 under Minn. Stat. Sec. 394.34; recorded with the Wright County Recorder May 20, 2026 as Document #A1603075
- What happened next
- County staff and Planning Commission directed to study data centers and propose amendments to the County's official controls
Campuses in reach
Scannell Technology Park - Building 3Wright CountyAnnounced·Scannell PropertiesTarget-Elk RiverSherburne CountyAnnounced·TargetUHG - Elk RiverSherburne CountySite permit·≈27–120 MWMN2 - Flexential Chaska MN Data Center PoPCarver CountyBuilding permit·≈17–78 MWMSP CampusCarver CountyAnnounced·CloudHQStreamCarver CountyAnnounced·7 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Wright County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (3 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.