Pacific moratorium
Pacific, Missouri paused new data center approvals on 4 Aug 2026, citing specific project and water use. It covers 1 tracked campus. Checked 23 Nov 2026
In force since 4 Aug 2026No end date on record
The facts
- Passed by
- Board of Aldermen, 4 Aug 2026
- Term
- One year, unless ended earlier by majority vote
- Legal basis
- Board of Aldermen ordinance (number not found in coverage reviewed)
- What happened next
- Board to research and develop data center policies during the stay
- Applies to
- Beltline Energy data center rezoning application (public hearing proceeding separately)
- Reason
- Beltline Energy data center rezoning application pending; opposition from Pacific ROOT Coalition
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Pacific votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.