Oppidan Data Center

A data center campus in Berkeley, Missouri, built by Oppidan. It has had a site permit since March 2024 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Mar 2024
Not on recordCapacity
1Public records
15Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitMar 2024
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from March 2024. A building permit is the next step. The City of St. Peters has a moratorium in force 22 km away

St. Louis County, MissouriParcel, substation and lines

The record

Owner
Oppidan
Stage
Site permit
Capacity
Not on record
Public records
1
Latest record
5 Mar 2024
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Oppidan Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Oppidan Data Center?
Oppidan, according to public records.
How big is it?
Not on record
Has it been approved?
Yes. It has had a site permit since March 2024.
Is there local opposition?
Yes. 12 moratoria in force and 1 pending and 2 ended nearby.