Oppidan Data Center
A data center campus in Berkeley, Missouri, built by Oppidan. It has had a site permit since March 2024 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Mar 2024
Not on recordCapacity
1Public records
15Moratoria nearby
How far along
- Announced
- Zoning
- Site permitMar 2024
- Building permit
- Construction
- Operating
The site permit dates from March 2024. A building permit is the next step. The City of St. Peters has a moratorium in force 22 km away
St. Louis County, MissouriParcel, substation and lines
The record
- Owner
- Oppidan
- County
- St. Louis County, MO
- Stage
- Site permit
- Capacity
- Not on record
- Public records
- 1
- Latest record
- 5 Mar 2024
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Utility, substation and 1 public record for Oppidan Data CenterOpen the app, freeStart Pro · $299/mo
Opposition nearby
City of St. Peters moratorium22 kmIn forceCity of St. Charles moratorium26 kmEndedSt. Charles County moratorium26 kmIn forcePacific moratorium31 kmIn force
Opposition in MissouriKnow when this campus moves
Check your email to finish
Questions
Who owns Oppidan Data Center?
Oppidan, according to public records.
How big is it?
Not on record
Has it been approved?
Yes. It has had a site permit since March 2024.
Is there local opposition?
Yes. 12 moratoria in force and 1 pending and 2 ended nearby.