Sayreville moratorium
Sayreville, New Jersey paused new data center approvals on 20 Jul 2026, citing grid and power and water use. Checked 23 Nov 2026
In force since 20 Jul 2026No end date on record
The facts
- Reason
- Study of electric-grid, water, stormwater, fiscal, land-use, noise, and environmental effects of data center development
- Term
- 18 months from adoption; the ordinance also requires publication and mayoral approval, and the copy reviewed does not show the mayoral approval date
- Legal basis
- Ordinance 15-26 (Borough of Sayreville), a temporary prohibition on data center development in every zone, including the Hercules Redevelopment Area, for 18 months, introduced 2026-06-15 and adopted on final reading 2026-07-20
Campuses in reach
PNJ-01 / -02Middlesex CountyAnnounced·ChirisaQuality Technology Services PiscatawayMiddlesex CountySite permit·52 MWCoreWeave Kenilworth CampusUnion CountyConstruction·250 MWMerck Sharp & Dohme - K-22 Data CenterUnion CountySite permit·Merck Sharp Dohme K 22 Data CenterEquinixHudson CountySite permit·≈16–73 MWNew York 2Hudson CountySite permit·≈6–28 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Sayreville votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.