Data center projects in New Jersey

8 campuses are planned or being built in New Jersey, with 302 MW disclosed so far. 7 have a site permit or later. Checked 27 Nov 2026

8Campuses
302 MWDisclosed capacity
2Under construction
5Moratoria in force
New Jersey
New JerseyOpen map
One or two campusesThree or more

Where New Jersey stands

Top counties

Track New Jersey in the app, free

Check your email to finish

What the stages mean

  • AnnouncedNamed by the owner or an official
  • ZoningRezoning filed or approved
  • Site permitSite plan or land use approved
  • Building permitPermit to build issued
  • ConstructionWork on site has started
  • OperatingRunning and taking load

Questions

How many data centers are being built in New Jersey?

8 campuses are planned or being built. 2 are under construction and 7 have a site permit or later

Announced 1 · Site permit 5 · Construction 2

Which New Jersey counties have the most?
Who is building them?
How do you know a project is real?

Every campus here is matched to at least one public filing: an announcement, a rezoning, a site plan or a permit. As of 2026-11-27, Wattlas lists 180 campuses in New Jersey, 155 of them operating and 17 reported plans not yet confirmed by a filing