Data center projects in New Jersey
8 campuses are planned or being built in New Jersey, with 302 MW disclosed so far. 7 have a site permit or later. Checked 27 Nov 2026
8Campuses
302 MWDisclosed capacity
2Under construction
5Moratoria in force
New JerseyOpen map
One or two campusesThree or more
CoreWeave Kenilworth Campus
CoreWeaveUnionConstruction250 MWVineland Data Center PipelineSouth Jersey GasCumberlandSite permit≈90–410 MWQuality Technology Services Piscataway
QTSMiddlesexSite permit52 MWEquinix
EquinixHudsonSite permit≈16–73 MWNew York 2
CoresiteHudsonSite permit≈6–28 MW
Utility, substation and records for every rowUtility and substationStart Pro · $299/mo
Merck Sharp & Dohme - K-22 Data CenterMerck Sharp Dohme K 22 Data CenterUnionSite permitNebius Vineland Data CenterDataoneCumberlandConstructionPNJ-01 / -02ChirisaMiddlesexAnnouncedNo campuses match
Where New Jersey stands
Top counties
- Cumberland2
- Hudson2
- Middlesex2
- Union2
Top owners
CoreWeave250 MW1- Shamrockconstruction Group250 MW1
QTS52 MW1
- ChirisaNot on record1
CoresiteNot on record1
Track New Jersey in the app, free
Check your email to finish
What the stages mean
- AnnouncedNamed by the owner or an official
- ZoningRezoning filed or approved
- Site permitSite plan or land use approved
- Building permitPermit to build issued
- ConstructionWork on site has started
- OperatingRunning and taking load
Questions
How many data centers are being built in New Jersey?
8 campuses are planned or being built. 2 are under construction and 7 have a site permit or later
Announced 1 · Site permit 5 · Construction 2
Which New Jersey counties have the most?
Who is building them?
How do you know a project is real?
Every campus here is matched to at least one public filing: an announcement, a rezoning, a site plan or a permit. As of 2026-11-27, Wattlas lists 180 campuses in New Jersey, 155 of them operating and 17 reported plans not yet confirmed by a filing