Nebius
Nebius has 5 campuses in 3 states: 3 operating and 2 planned or building, about 300 MW in the pipeline. Checked 27 Nov 2026
5Campuses
3States
≈300 MWIn the pipeline
0Moved in the last 90 days
Footprint
United StatesOpen map
One or two campusesThree or more
By stage
By state
Every campus
Nebius Vineland Data CenterVineland, NJConstructionJul 2026Nebius Birmingham Data CenterJefferson County, ALAnnounced300 MWNebius Independence DC4Independence, MONebius Kansas CityKansas, MONebius New JerseyVineland, NJ
Source filings, power and grid detail for all 5 Nebius campusesFilings and grid detailStart Pro · $299/mo
Who works with Nebius
- Contractors and engineers across their sites
- Tenants
- Utilities and grid requests
Know when Nebius files something
Check your email to finish
Jobs at Nebius7 open roles
Questions
How many data centers does Nebius have?
As of 2026-11-27, Wattlas lists 5 US data center campuses associated with Nebius: 2 confirmed pipeline campuses (1 under construction), 3 operating sites, and 0 tracker-reported plans.