Bitpower Data Center

An estimated 230–1,100 MW data center campus in Anaconda, Montana, built by FX Solutions. It has had a site permit since January 2018 and has 2 public records behind it. Checked 27 Nov 2026

Site permitStage since Jan 2018
≈230–1,100 MWCapacity, our estimate
2Public records
4Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitJan 2018
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from January 2018. A building permit is the next step. Butte-Silver Bow has a moratorium pending 48 km away

Deer Lodge County, MontanaParcel, substation and lines

The record

Owner
FX Solutions
County
Deer Lodge County, MT
Stage
Site permit
Capacity
≈230–1,100 MW
Public records
2
Latest record
25 Jan 2018
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for Bitpower Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Bitpower Data Center?
FX Solutions, according to public records.
How big is it?
About 230–1,100 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had a site permit since January 2018.
Is there local opposition?
Yes. 1 moratorium in force and 2 pending and 1 ended nearby.