An estimated 94–440 MW data center campus in Hardin, Montana, built by Liefern. It has had a site permit since October 2020 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Oct 2020
≈94–440 MWCapacity, our estimate
1Public records
7Moratoria nearby
How far along
- Announced
- Zoning
- Site permitOct 2020
- Building permit
- Construction
- Operating
The site permit dates from October 2020. A building permit is the next step. Butte-Silver Bow has a moratorium pending 395 km away
Big Horn County, MontanaParcel, substation and lines
The record
- Owner
- Liefern
- County
- Big Horn County, MT
- Stage
- Site permit
- Capacity
- ≈94–440 MW
- Public records
- 1
- Latest record
- 9 Oct 2020
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Utility, substation and 1 public record for Liefern Data CenterOpen the app, freeStart Pro · $299/mo
Know when this campus moves
Check your email to finish
Questions
Who owns Liefern Data Center?
Liefern, according to public records.
How big is it?
About 94–440 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had a site permit since October 2020.
Is there local opposition?
Yes. 1 moratorium in force and 1 pending and 5 ended nearby.