Data Center

An estimated 10–45 MW data center campus in Lithia Springs, Georgia, built by Ipi Legacy Rock House. It has had a site permit since August 2009 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Aug 2009
≈10–45 MWCapacity, our estimate
1Public records
4Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitAug 2009
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from August 2009. A building permit is the next step. Paulding County has a moratorium in force 23 km away

Douglas County, GeorgiaParcel, substation and lines

The record

Owner
Ipi Legacy Rock House
Stage
Site permit
Capacity
≈10–45 MW
Public records
1
Latest record
24 Aug 2009
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Data Center?
Ipi Legacy Rock House, according to public records.
How big is it?
About 10–45 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had a site permit since August 2009.
Is there local opposition?
Yes. 2 moratoria in force and 2 ended nearby.