A data center campus in Lithia Springs, Georgia, built by Amazon. It has had a site permit since November 2024 and has 8 public records behind it. Checked 27 Nov 2026

Site permitStage since Nov 2024
Not on recordCapacity
8Public records
4Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitNov 2024
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from November 2024. A building permit is the next step. Paulding County has a moratorium in force 23 km away

Douglas County, GeorgiaParcel, substation and lines

The record

Owner
Amazon
Stage
Site permit
Capacity
Not on record
Public records
8
Latest record
9 Nov 2024
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
8 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 8 public records for Data center projectOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Data center project?
Amazon, according to public records.
How big is it?
Not on record
Has it been approved?
Yes. It has had a site permit since November 2024.
Is there local opposition?
Yes. 2 moratoria in force and 2 ended nearby.