Project Walsh Data Center

An estimated 14–66 MW data center campus in Lithia Springs, Georgia, built by Pricewaterhouse Coopers. It has had a site permit since February 2009 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Feb 2009
≈14–66 MWCapacity, our estimate
1Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permitFeb 2009
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from February 2009. A building permit is the next step

Douglas County, GeorgiaParcel, substation and lines

The record

Owner
Pricewaterhouse Coopers
Stage
Site permit
Capacity
≈14–66 MW
Public records
1
Latest record
3 Feb 2009
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Project Walsh Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Project Walsh Data Center?
Pricewaterhouse Coopers, according to public records.
How big is it?
About 14–66 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had a site permit since February 2009.
Is there local opposition?
Yes. 2 opposition records on file.