Data center project

A 26 MW data center campus in Elk Grove, Illinois, built by Centersquare. It was announced in 2025 and has 1 public record behind it. Checked 27 Nov 2026

AnnouncedStage since 2025
26 MWCapacity, as stated
1Public records

How far along

  1. Announced2025
  2. Zoning
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

The announced dates from 2025. A rezoning or site permit is the next step

Cook County, IllinoisParcel, substation and lines

The record

Stage
Announced
Capacity
26 MW
Public records
1
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Data center projectOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Data center project?
Centersquare, according to public records.
How big is it?
26 MW, as stated in a public filing.
Has it been approved?
Not yet. It was announced in 2025.
Is there local opposition?
Not on record