Chicago CH3 Data Center

A 30 MW data center campus in Elk Grove, Illinois, built by Digital Realty. It has had a building permit since June 2025 and has 7 public records behind it. Checked 27 Nov 2026

Building permitStage since Jun 2025
30 MWCapacity, as stated
7Public records
1Moratorium pending nearby

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permitJun 2025
  5. Construction
  6. Operating

The building permit dates from June 2025. Construction is the next step. Chicago has a moratorium pending 7 km away

Cook County, IllinoisParcel, substation and lines

The record

Stage
Building permit
Capacity
30 MW
Public records
7
Latest record
25 Jun 2025
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
7 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 7 public records for Chicago CH3 Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Chicago CH3 Data Center?
Digital Realty, according to public records.
How big is it?
30 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a building permit since June 2025.
Is there local opposition?
Yes. 1 moratorium pending nearby.