Project Celtic Phases 1 & 2 - Novec Bridging Power (EPLAN-2026-0098)

A 117 MW data center campus in Loudoun County, Virginia, built by Nova Building 4. It has had a building permit since January 2025 and has 2 public records behind it. Checked 27 Nov 2026

Building permitStage since Jan 2025
117 MWCapacity, as stated
2Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permitJan 2025
  5. Construction
  6. Operating

The building permit dates from January 2025. Construction is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Nova Building 4
Stage
Building permit
Capacity
117 MW
Public records
2
Latest record
15 Jul 2026
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for Project Celtic Phases 1 & 2 - Novec Bridging Power (EPLAN-2026-0098)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Project Celtic Phases 1 & 2 - Novec Bridging Power (EPLAN-2026-0098)?
Nova Building 4, according to public records.
How big is it?
117 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a building permit since January 2025.
Is there local opposition?
Yes. 2 opposition records on file.