Amazon IAD-667, IAD-668, IAD-669, IAD-670, AND IAD-671

An estimated 150–310 MW data center campus in Leesburg, Virginia, built by Areit Nova I. It has had a building permit since January 2024 and has 2 public records behind it. Checked 27 Nov 2026

Building permitStage since Jan 2024
≈150–310 MWCapacity, our estimate
2Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permitJan 2024
  5. Construction
  6. Operating

The building permit dates from January 2024. Construction is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Areit Nova I
Stage
Building permit
Capacity
≈150–310 MW
Public records
2
Latest record
29 Jan 2026
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for Amazon IAD-667, IAD-668, IAD-669, IAD-670, AND IAD-671Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Amazon IAD-667, IAD-668, IAD-669, IAD-670, AND IAD-671?
Areit Nova I, according to public records.
How big is it?
About 150–310 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a building permit since January 2024.
Is there local opposition?
Yes. 2 opposition records on file.