INOVA Health Systems Phase 1 (EPLAN-2025-0090)

An estimated 75–340 MW data center campus in Arcola, Virginia, built by Amazon. It has had a rezoning request on file since June 2025 and has 3 public records behind it. Checked 27 Nov 2026

ZoningStage since Jun 2025
≈75–340 MWCapacity, our estimate
3Public records
2Opposition records

How far along

  1. Announced
  2. ZoningJun 2025
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

The zoning dates from June 2025. Zoning approval is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Amazon
Stage
Zoning
Capacity
≈75–340 MW
Public records
3
Latest record
2 Jun 2025
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
3 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 3 public records for INOVA Health Systems Phase 1 (EPLAN-2025-0090)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns INOVA Health Systems Phase 1 (EPLAN-2025-0090)?
Amazon, according to public records.
How big is it?
About 75–340 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Not yet. It has had a rezoning request on file since June 2025.
Is there local opposition?
Yes. 2 opposition records on file.