Yondr Data Center
A 336 MW data center campus in Aldie, Virginia, built by Yondr. It has had a site permit since June 2024 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Jun 2024
336 MWCapacity, as stated
1Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permitJun 2024
- Building permit
- Construction
- Operating
The site permit dates from June 2024. A building permit is the next step
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- Yondr
- County
- Loudoun County, VA
- Stage
- Site permit
- Capacity
- 336 MW
- Public records
- 1
- Latest record
- 7 Jun 2024
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Know when this campus moves
Check your email to finish
Questions
Who owns Yondr Data Center?
Yondr, according to public records.
How big is it?
336 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since June 2024.
Is there local opposition?
Yes. 2 opposition records on file.