An estimated 22–100 MW data center campus in Loudoun County, Virginia, built by Delta Management. It has had a rezoning request on file since October 2024 and has 4 public records behind it. Checked 27 Nov 2026
ZoningStage since Oct 2024
≈22–100 MWCapacity, our estimate
4Public records
2Opposition records
How far along
- Announced
- ZoningOct 2024
- Site permit
- Building permit
- Construction
- Operating
The zoning dates from October 2024. Zoning approval is the next step
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- Delta Management
- County
- Loudoun County, VA
- Stage
- Zoning
- Capacity
- ≈22–100 MW
- Public records
- 4
- Latest record
- 30 Oct 2024
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
4 records
- Record 1
- Record 2
- Record 3
Utility, substation and 4 public records for Mercure Business Park Lot 22 (EPLAN-2024-0161)Open the app, freeStart Pro · $299/mo
Know when this campus moves
Check your email to finish
Questions
Who owns Mercure Business Park Lot 22 (EPLAN-2024-0161)?
Delta Management, according to public records.
How big is it?
About 22–100 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Not yet. It has had a rezoning request on file since October 2024.
Is there local opposition?
Yes. 2 opposition records on file.