Briarfield Lane Informal Proffer (ZCOR-2024-0060)

An estimated 39–180 MW data center campus in Loudoun County, Virginia, built by Yondr. It has had zoning approval since February 2024 and has 1 public record behind it. Checked 27 Nov 2026

ZoningStage since Feb 2024
≈39–180 MWCapacity, our estimate
1Public records
2Opposition records

How far along

  1. Announced
  2. ZoningFeb 2024
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

The zoning dates from February 2024. A site permit is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Yondr
Stage
Zoning
Capacity
≈39–180 MW
Public records
1
Latest record
29 Feb 2024
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Briarfield Lane Informal Proffer (ZCOR-2024-0060)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Briarfield Lane Informal Proffer (ZCOR-2024-0060)?
Yondr, according to public records.
How big is it?
About 39–180 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had zoning approval since February 2024.
Is there local opposition?
Yes. 2 opposition records on file.