Microsoft Blue Ridge (IAD11-12-13) Data Center

An estimated 20–43 MW data center campus in Aldie, Virginia, built by Microsoft. It has had a site permit since May 2024 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since May 2024
≈20–43 MWCapacity, our estimate
1Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permitMay 2024
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from May 2024. A building permit is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Stage
Site permit
Capacity
≈20–43 MW
Public records
1
Latest record
9 May 2024
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Microsoft Blue Ridge (IAD11-12-13) Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Microsoft Blue Ridge (IAD11-12-13) Data Center?
Microsoft, according to public records.
How big is it?
About 20–43 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since May 2024.
Is there local opposition?
Yes. 2 opposition records on file.