IAD11 Data Center
An estimated 20–43 MW data center campus in Dulles, Virginia, built by Microsoft. It has had a site permit since July 2024 and has 4 public records behind it. Checked 27 Nov 2026
Site permitStage since Jul 2024
≈20–43 MWCapacity, our estimate
4Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permitJul 2024
- Building permit
- Construction
- Operating
The site permit dates from July 2024. A building permit is the next step
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- Microsoft
- County
- Loudoun County, VA
- Stage
- Site permit
- Capacity
- ≈20–43 MW
- Public records
- 4
- Latest record
- 1 Jul 2024
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
4 records
- Record 1
- Record 2
- Record 3
Know when this campus moves
Check your email to finish
Questions
Who owns IAD11 Data Center?
Microsoft, according to public records.
How big is it?
About 20–43 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since July 2024.
Is there local opposition?
Yes. 2 opposition records on file.