US data center construction pipeline by state (2026)
State-by-state breakdown of confirmed planned and under-construction US data center projects, disclosed MW, permit progress, and local moratorium risk.
Headlines about US data center construction often blend press releases, operating colocation buildings, and speculative utility queue requests into a single number. Separating filing-confirmed pipeline campuses (announced with a public filing, in zoning, permitted, or under construction) shows a sharper map of where mission-critical construction is actually moving—and where local moratoria are slowing new entitlements.
The state table below summarizes confirmed US pipeline campuses in Wattlas’s public pipeline directory alongside active local moratoria from the US Data Center Moratorium Tracker as of late November 2026. Every state link opens the live, daily-refreshed state hub.
Top 15 US states by confirmed data center pipeline
Campuses are ranked by confirmed public pipeline count (projects with a verified developer/owner, jurisdiction, and at least one official public filing). Site permit+ counts campuses that have already cleared site permitting, building permitting, or broken ground.
| State | Confirmed pipeline | Under construction | Site permit+ | Disclosed MW (sites reporting) | Active local moratoria | State hub |
|---|---|---|---|---|---|---|
| Virginia | 298 | 34 | 192 | 12,469 MW (44) | 5 | Virginia projects |
| Texas | 143 | 15 | 95 | 28,752 MW (69) | 3 | Texas projects |
| Georgia | 88 | 5 | 28 | 21,631 MW (35) | 45 | Georgia projects |
| Pennsylvania | 65 | 5 | 18 | 22,926 MW (22) | 19 | Pennsylvania projects |
| Minnesota | 60 | 1 | 17 | 3,104 MW (18) | 27 | Minnesota projects |
| Illinois | 59 | 6 | 38 | 4,246 MW (28) | 24 | Illinois projects |
| Ohio | 59 | 2 | 41 | 11,307 MW (21) | 149 | Ohio projects |
| Arizona | 36 | 3 | 32 | 2,228 MW (14) | 1 | Arizona projects |
| Indiana | 23 | 1 | 7 | 1,668 MW (4) | 24 | Indiana projects |
| Nevada | 22 | 3 | 6 | 4,503 MW (7) | 5 | Nevada projects |
| California | 18 | 2 | 13 | 928 MW (7) | 20 | California projects |
| Colorado | 17 | 1 | 15 | 478 MW (5) | 26 | Colorado projects |
| New York | 15 | 0 | 3 | 1,563 MW (8) | 27 | New York projects |
| North Carolina | 14 | 1 | 9 | 658 MW (4) | 56 | North Carolina projects |
| Iowa | 12 | 3 | 8 | 1,042 MW (4) | 41 | Iowa projects |
Snapshot from Wattlas’s public state directory (checked November 26, 2026). Disclosed MW sums only filings or announcements that state a number and excludes sites whose capacity is estimated or undisclosed; see Data center megawatts explained.
Three patterns across the state rankings
1. Permit-heavy core markets vs early-entitlement expansion states
Virginia, Texas, Ohio, Illinois, and Arizona have a high share of campuses already at site permit, building permit, or construction—meaning land use is largely settled and procurement, electrical, and commissioning work is active. By contrast, Georgia, Pennsylvania, Minnesota, and Indiana carry large early-stage zoning and announced queues where individual projects still face public hearings and grid studies.
2. Megawatt concentration is shifting toward gigawatt-scale power corridors
Texas (28.8 GW disclosed across 69 reporting sites), Pennsylvania (22.9 GW across 22 sites), and Georgia (21.6 GW across 35 sites) surpass Virginia in disclosed pipeline MW despite fewer individual filings. Large AI campuses seeking 200 MW to 1+ GW blocks are clustering around ERCOT, PJM transmission corridors, and behind-the-meter generation sites. See Large load interconnection explained and Phantom data centers: the record test for why requested MW shrinks between queue entry and energization.
3. Local moratoria are concentrated in high-growth Midwest and Southeast states
Ohio (149 active local measures), North Carolina (56), Georgia (45), Iowa (41), New York (27), Minnesota (27), Colorado (26), Illinois (24), and Indiana (24) have the heaviest local moratorium activity. As detailed in 41% of US pipeline data centers sit in a county with a moratorium, a municipal pause does not automatically halt projects in neighboring cities or already-permitted builds, so site teams must verify jurisdiction boundaries per parcel.
Explore by state, market, or county
- Other active build states: Missouri, Alabama, Maryland, Oregon, Kentucky, Florida, Wyoming, and Tennessee.
- Metro power hubs: Compare 34 US regions by estimated GW, satellite land clearing, water stress, and opposition in US data center markets.
- County concentration: Inspect top build counties in the US data center counties index.
- Active hiring: Track where operators and contractors are staffing up in US data center jobs.
- Compare data platforms: See how Wattlas stacks up against DC Byte, datacenterHawk, Cleanview, and Blackridge in the comparison hub, or inspect three unlocked Pro records.