Vantage Data Centers VA11, VA12, VA13, VA14, & VA15
A 206 MW data center campus in Sterling, Virginia, run by Vantage. It is listed as operating and has 1 public record behind it. Checked 27 Nov 2026
OperatingStatus
206 MWCapacity, as stated
1Public records
2Opposition records
How far along
- Operating
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- Vantage
- County
- Loudoun County, VA
- Status
- Capacity
- 206 MW
- Public records
- 1
- Latest record
- 7 Feb 2019
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Utility, substation and 1 public record for Vantage Data Centers VA11, VA12, VA13, VA14, & VA15Open the app, freeStart Pro · $299/mo
Nearby campuses
Sentinel Ashburn Nexus≈5 kmSite permit·Sentinel Ashburn NexusVantage VA16 Campus≈5 kmBuilding permit·VantageAmerica Online Technology Center (STPR-2006-0026)≈5 kmSite permit·American Real Estate PartnersSterling Data Center (Menlo Digital)≈5 kmAnnounced·Menlo Equities
All campuses in Loudoun CountyMore from Vantage
Vantage OH2 Millersport Campus696 MWSite permit·Millersport, OHVWPP Belmont Innovation (PCOR-2023-0016)≈240–1,100 MWZoning·Loudoun County, VAVantage Data Center - Doughlasville≈210–970 MWZoning·Douglas County, GAVantage Data Center AZ14≈120–570 MWSite permit·Unknown, AZ
All 71 campusesKnow when this campus moves
Check your email to finish
Questions
Who owns Vantage Data Centers VA11, VA12, VA13, VA14, & VA15?
Vantage, according to public records.
How big is it?
206 MW, as stated in a public filing.
Has it been approved?
Yes. It is listed as operating.
Is there local opposition?