Atlanta

Atlanta is market 5 of 34: about 20.9 GW across 56 campuses in 20 counties. 3 under construction and 5 moratoria in force. Checked 28 Nov 2026

56Campuses
≈20.9 GWIn the pipeline
3Under construction
5Moratoria in force
All 56 campuses
Rumble Technology Park≈670–3,100 MWAnnounced·GoogleWallace Jackson Data Center Campus≈620–2,900 MWZoning·Wallace JacksonAmazon Data Services Alcovy Road campus≈360–1,600 MWAnnounced·JBW Investments Universal Planning and DevelopmentAvemore Data Park≈340–1,600 MWZoning·Atlas DevelopmentSoutheast Data Center campus340 MWZoning·Oceanic Data CentersATL03/Red Oak300 MWZoning·TA RealtyT5@ATL IV300 MWZoning·T5EdgeConneX ATL11-13270 MWAnnounced·EdgeConneXATL2 East≈250–1,100 MWZoning·QTSEquinix Atlanta Data Center240 MWSite permit·EquinixSDC Atla240 MWSite permit·StreamStonewall Tell Data Center≈240–1,100 MWZoning·RSC Investment ManagementVantage Data Center - Doughlasville≈210–970 MWZoning·VantageDigital Realty Fort Gillem Campus (ATL15/16)200 MWSite permit·Digital RealtyProject Indo200 MWZoning·DataBankThe Crossing Business Park≈190–860 MWZoning·B9 Union City OwnerRock House Road Data Center Site≈180–840 MWZoning·Taylor MathisProject Edged / Tilford Yards Technology Park168 MWAnnounced·EdgedData center project≈160–330 MWSite permit·AmazonLithia Springs Data Center160 MWZoning·At TKingston Technology Hub150 MWZoning·Thor EquitiesDC BLOX Atlanta West120 MWConstruction·DC BloxEdgeConneX ATL11, LLC≈120–260 MWSite permit·EdgeConneXCCO06 Data Center≈110–230 MWSite permit·MicrosoftProject Rita96 MWZoning·MicrosoftFTY01 Data Center≈57–120 MWBuilding permit·MicrosoftVantage Data Center - Stacks Rd≈57–120 MWSite permit·VantageVantage Data Center - Westlake≈57–120 MWSite permit·VantageAligned Data Centers (Atl) Propco, LLC≈46–97 MWSite permit·AlignedData Center Fulton, LLC40 MWSite permit·Data Center FultonFlexential Corporation36 MWSite permit·FlexentialProject Walsh Data Center≈14–66 MWSite permit·Pricewaterhouse CoopersData Center≈10–45 MWSite permit·Ipi Legacy Rock HouseEast Point Data Center≈10–22 MWAnnounced·Lincoln PropertyMicrosoft: Union City Bldg 1≈4–18 MWZoning·MicrosoftAdp Data Center (DC1)≈3–7 MWSite permit·Aiiso Doreen 590075 South Data Center CampusNot on recordZoning·HillwoodAmazon Data Services, Inc. ATL089 CampusNot on recordSite permit·AmazonAmazon Web Services Butts County data center campusNot on recordAnnounced·AmazonBig Power Developments 5, LLC Data Center (S2025-13)Not on recordZoning·Big Power Developments 5Building Corner - Amazon Data CenterNot on recordAnnounced·AmazonData center projectNot on recordSite permit·AmazonDouglasville Data CenterNot on recordAnnounced·MicrosoftEast Village Dothan, LLC Data Center (Z2026-57)Not on recordZoning·East Village DothanLithia Springs Campus Data Center: ATL5Not on recordConstruction·DataBankQTS Atlanta-Fayetteville DC3Not on recordConstruction·QTSRiver ParkNot on recordAnnounced·River Park IndustrialSocial Circle Technology ParkNot on recordAnnounced·SC InfrastructureStream Data Center: GANot on recordZoning·StreamT5@ATL IIINot on recordSite permit·T5Voss II- Expansion Network Data CenterNot on recordSite permit·At T Mobility

The shape of the market

By stage

  • Announced11
  • Zoning22
  • Site permit19
  • Building permit1
  • Construction3

Stated and estimated

  • Stated on record5.3 GW
  • Our estimate≈15.6 GW

By county

Power in this market
  • Utilities serving these campuses
  • Grid requests on file
  • Substations, water stress and flood
  • Download this market as CSV
Power, water and flood for AtlantaOpen the app, freeStart Pro · $299/mo

Track Atlanta in the app, free

Check your email to finish

Questions

How many data centers are in Atlanta?

61 tracked pipeline campuses (20.9 GW estimated total, 5,320 MW reported) across 20 counties in Georgia. Key signals: 14 sites showing earthwork in satellite imagery, 9 active/extended moratoria, 7 pipeline sites in high/extremely high water stress.

Estimated pipeline MW combines reported capacity (5,320 MW) with estimates from floor area, acreage, investment or backup generation. 35.9% of monitored sites show clearing.

Who is building the most?
Which counties have paused new data centers?
How is this market drawn?

Atlanta is the 20 counties around its campuses in Georgia, in Non-ISO. It ranks 5 of 34 markets by estimated pipeline.

How large is the Atlanta data center pipeline?

Wattlas tracks 61 upcoming pipeline campuses in Atlanta (25 verified, 3 under construction, 22 permitted), representing 5,320 MW in reported capacity and 20,925 MW total estimated pipeline. Projects with the largest reported figures include Bridgeport (Revised) (1,000+ MW), Hampton Technology Park (1,000+ MW), Digital Realty Stilesboro campus (1,000+ MW).

What are industrial power rates and serving utilities in Atlanta?

Atlanta sits in Non-ISO. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.

What local opposition, moratoria, or water risks affect Atlanta data centers?

Across tracked campuses in Atlanta, Wattlas links 9 active or extended moratoria (17 total) and 19 public petitions. On physical site risk, 7 of 61 pipeline campuses sit in High or Extremely High baseline water stress (0 Extremely High). Floodplain and ozone screening are included in Wattlas access.

How many Atlanta data center sites show active satellite land clearing?

Of 39 pinpointed pipeline sites monitored with satellite imagery in Atlanta, 14 (35.9%) show active earthwork or pad expansion, including 12 sites clearing ahead of a reported construction stage.