Salt Lake City / Silicon Slopes
Salt Lake City / Silicon Slopes is market 4 of 34: about 21.6 GW across 8 campuses in 8 counties. 2 under construction and 1 moratorium in force. Checked 28 Nov 2026
Largest campuses
The shape of the market
By stage
- Announced4
- Site permit2
- Construction2
Stated and estimated
- Stated on record10.0 GW
- Our estimate≈11.6 GW
Who is building
Tract1,700 MW2QTSNot on record2
Creekstone Energy10,000 MW1- Fibernet10,000 MW1
O Leary Digital7,500 MW1
By county
- Utah4
- Salt Lake2
- Box Elder1
- Millard1
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Salt Lake City / Silicon Slopes in the app, free
Questions
How many data centers are in Salt Lake City / Silicon Slopes?
11 tracked pipeline campuses (21.6 GW estimated total, 10,000 MW reported) across 8 counties in Utah. Key signals: 1 site showing earthwork in satellite imagery, 1 active/extended moratorium, 10 pipeline sites in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (10,000 MW) with estimates from floor area, acreage, investment or backup generation. 20.0% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
1 moratorium is in force in Salt Lake City / Silicon Slopes, covering 1 campus. 1 moratorium and 6 petitions are on record across the market. 10 of 11 campuses sit in high water stress.
How is this market drawn?
How large is the Salt Lake City / Silicon Slopes data center pipeline?
Wattlas tracks 11 upcoming pipeline campuses in Salt Lake City / Silicon Slopes (3 verified, 2 under construction, 3 permitted), representing 10,000 MW in reported capacity and 21,575 MW total estimated pipeline. Projects with the largest reported figures include Creekstone Energy Delta Gigasite (1,000+ MW), Stratos Project (1,000+ MW), Fibernet MercuryDelta Campus (1,000+ MW).
What are industrial power rates and serving utilities in Salt Lake City / Silicon Slopes?
Salt Lake City / Silicon Slopes sits in Non-ISO. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Salt Lake City / Silicon Slopes data centers?
Across tracked campuses in Salt Lake City / Silicon Slopes, Wattlas links 1 active or extended moratorium (1 total) and 6 public petitions. On physical site risk, 10 of 11 pipeline campuses sit in High or Extremely High baseline water stress (1 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Salt Lake City / Silicon Slopes data center sites show active satellite land clearing?
Of 5 pinpointed pipeline sites monitored with satellite imagery in Salt Lake City / Silicon Slopes, 1 (20.0%) show active earthwork or pad expansion, including 1 site clearing ahead of a reported construction stage.