In forceMoratorium

Hazle Township moratorium

Hazle Township, Pennsylvania paused new data center approvals on 8 Jun 2026 for 6 months, citing specific project and zoning and rules. It covers 1 tracked campus. Checked 23 Nov 2026

Started 8 Jun 20266 of 6 months passedEnds 5 Dec 2026

The facts

Passed by
Hazle Township Board of Supervisors, 8 Jun 2026
Applies to
NorthPoint Development's proposed 'Project Hazelnut' data-center campus, previously denied by the township and by a county court.
Reason
Followed sustained community opposition ("Project Hazelnot") to NorthPoint Development's proposed ~1,300-acre, 15-building "Project Hazelnut" data-center campus with substation, which the township had already rejected in November 2025 and which a Luzerne County judge ruled against in spring 2026.
Term
A 180-day period for preparing a curative amendment was reported after the June 8 vote; the solicitor described protection against zoning-validity challenges. The precise legal interval and application-level effect are not established by the retained report.
Legal basis
Municipal curative amendment adopted by the Hazle Township Board of Supervisors, temporarily invalidating portions of the township zoning ordinance for 180 days on the stated grounds that the ordinance is deficient because it does not address data centers (instrument number not located).
What happened next
Supervisors unanimously adopted a resolution initiating a 180-day curative process, according to June reporting. The report describes protection against zoning-validity challenges; it does not establish a blanket bar on new data-center applications.

Know when Hazle Township votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Hazle Township paused data centers?