Data center project
A 79 MW data center campus in Leesburg, Virginia, built by Compass Datacenters Iad I. It has had a site permit since October 2022 and has 3 public records behind it. Checked 27 Nov 2026
Site permitStage since Oct 2022
79 MWCapacity, as stated
3Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permitOct 2022
- Building permit
- Construction
- Operating
The site permit dates from October 2022. A building permit is the next step
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- Compass Datacenters Iad I
- County
- Loudoun County, VA
- Stage
- Site permit
- Capacity
- 79 MW
- Public records
- 3
- Latest record
- 28 Oct 2022
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
3 records
- Record 1
- Record 2
- Record 3
Utility, substation and 3 public records for Data center projectOpen the app, freeStart Pro · $299/mo
Nearby campuses
Project Celtic Phases 1 & 2 - Novec Bridging Power (EPLAN-2026-0098)≈5 kmBuilding permit·Nova Building 4Luck Stone Corporation (LEGI-2023-0084)≈5 kmZoning·Luck StoneAmazon IAD-667, IAD-668, IAD-669, IAD-670, AND IAD-671≈5 kmBuilding permit·Areit Nova IOrme Farm Rezoning≈5 kmAnnounced·Van Metre Communities LLC Roy Barnett
All campuses in Loudoun CountyKnow when this campus moves
Check your email to finish
Questions
Who owns Data center project?
Compass Datacenters Iad I, according to public records.
How big is it?
79 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since October 2022.
Is there local opposition?
Yes. 2 opposition records on file.