JK Technology Park #2 (SPEX-2019-0031)

An estimated 32–150 MW data center campus in Arcola, Virginia, built by Hiddenwood Lane. It has had zoning approval since August 2019 and has 15 public records behind it. Checked 27 Nov 2026

ZoningStage since Aug 2019
≈32–150 MWCapacity, our estimate
15Public records
2Opposition records

How far along

  1. Announced
  2. ZoningAug 2019
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

The zoning dates from August 2019. A site permit is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Hiddenwood Lane
Stage
Zoning
Capacity
≈32–150 MW
Public records
15
Latest record
5 Aug 2026
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
15 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 15 public records for JK Technology Park #2 (SPEX-2019-0031)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns JK Technology Park #2 (SPEX-2019-0031)?
Hiddenwood Lane, according to public records.
How big is it?
About 32–150 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had zoning approval since August 2019.
Is there local opposition?
Yes. 2 opposition records on file.