Loudoun Center Lot 1 Ash 2 Data Center (SPAM-2019-0078)

A 96 MW data center campus in Ashburn, Virginia, built by Lohrasp Ventures. It has had a site permit since October 2019 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Oct 2019
96 MWCapacity, as stated
1Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permitOct 2019
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from October 2019. A building permit is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Stage
Site permit
Capacity
96 MW
Public records
1
Latest record
2 Oct 2019
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Loudoun Center Lot 1 Ash 2 Data Center (SPAM-2019-0078)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Loudoun Center Lot 1 Ash 2 Data Center (SPAM-2019-0078)?
Lohrasp Ventures, according to public records.
How big is it?
96 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since October 2019.
Is there local opposition?
Yes. 2 opposition records on file.