Loudoun Center Rhino PH 1 (STMP-2017-0013)

An estimated 120–560 MW data center campus in Ashburn, Virginia, built by Kaveh Ventures. It has had a site permit since December 2017 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Dec 2017
≈120–560 MWCapacity, our estimate
1Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permitDec 2017
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from December 2017. A building permit is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Kaveh Ventures
Stage
Site permit
Capacity
≈120–560 MW
Public records
1
Latest record
1 Dec 2017
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Loudoun Center Rhino PH 1 (STMP-2017-0013)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Loudoun Center Rhino PH 1 (STMP-2017-0013)?
Kaveh Ventures, according to public records.
How big is it?
About 120–560 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had a site permit since December 2017.
Is there local opposition?
Yes. 2 opposition records on file.