Loudoun Center ACC-9 Data Center (STPL-2013-0058)

A 27 MW data center campus in Ashburn, Virginia, built by Iskandar Ventures. It has had a site permit since December 2013 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Dec 2013
27 MWCapacity, as stated
1Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permitDec 2013
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from December 2013. A building permit is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Iskandar Ventures
Stage
Site permit
Capacity
27 MW
Public records
1
Latest record
26 Dec 2013
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Loudoun Center ACC-9 Data Center (STPL-2013-0058)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Loudoun Center ACC-9 Data Center (STPL-2013-0058)?
Iskandar Ventures, according to public records.
How big is it?
27 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since December 2013.
Is there local opposition?
Yes. 2 opposition records on file.