Data center projects in Utah
8 campuses are planned or being built in Utah, with 19.3 GW disclosed so far. 4 have a site permit or later. Checked 27 Nov 2026
8Campuses
19.3 GWDisclosed capacity
2Under construction
8Moratoria in force
UtahOpen map
One or two campusesThree or more
Creekstone Energy Delta Gigasite
Creekstone EnergyMillardConstruction10,000 MWStratos Project
O Leary DigitalBox ElderAnnounced7,500 MWTract Pole Canyon
TractUtahAnnounced1,700 MWSLC-03 Data Center
AlignedSalt LakeSite permit80 MWData center projectGrant MackaySalt LakeSite permit
QTSUtahConstructionQTS Eagle Mountain Data Center Campus
QTSUtahAnnouncedTract Pony Express
TractUtahAnnounced
Utility, substation and records for every rowUtility and substationStart Pro · $299/mo
Eagle Mountain Data Center InfrastructureNo campuses match
Where Utah stands
Top counties
- Utah4
- Salt Lake2
- Box Elder1
- Millard1
Top owners
Tract1,700 MW2QTSNot on record2
Creekstone Energy10,000 MW1- Fibernet10,000 MW1
O Leary Digital7,500 MW1
Track Utah in the app, free
Check your email to finish
What the stages mean
- AnnouncedNamed by the owner or an official
- ZoningRezoning filed or approved
- Site permitSite plan or land use approved
- Building permitPermit to build issued
- ConstructionWork on site has started
- OperatingRunning and taking load
Questions
How many data centers are being built in Utah?
8 campuses are planned or being built. 2 are under construction and 4 have a site permit or later
Announced 4 · Site permit 2 · Construction 2
Which Utah counties have the most?
Who is building them?
How do you know a project is real?