Houston
Houston is market 20 of 34: about 1.6 GW across 5 campuses in 7 counties. 0 under construction and 0 moratoria in force. Checked 28 Nov 2026
The shape of the market
By stage
- Announced1
- Site permit4
Stated and estimated
- Stated on recordNot on record
- Our estimate≈1.6 GW
Who is building
- SF Houh410 MW1
CleanSparkNot on record1
- DurotechNot on record1
- Eagles Nest 138Not on record1
- Montera Infrastructure IINot on record1
By county
- Harris3
- Brazoria2
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Houston in the app, free
Questions
How many data centers are in Houston?
5 tracked pipeline campuses (1.6 GW estimated total, 0 MW reported) across 7 counties in Texas. Key signals: 19 local petitions.
Estimated pipeline MW combines reported capacity (0 MW) with estimates from floor area, acreage, investment or backup generation. 0.0% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
No moratorium is in force in Houston today. 0 moratoria and 19 petitions are on record across the market. 0 of 5 campuses sit in high water stress.
How is this market drawn?
Houston is the 7 counties around its campuses in Texas, in ERCOT. It ranks 20 of 34 markets by estimated pipeline.
How large is the Houston data center pipeline?
Wattlas tracks 5 upcoming pipeline campuses in Houston (1 verified, 0 under construction, 4 permitted), representing 0 MW in reported capacity and 1,585 MW total estimated pipeline. Projects with the largest reported figures include Hockley Data Center (50–499 MW), CleanSpark Brazoria Data Center (50–499 MW).
What are industrial power rates and serving utilities in Houston?
Houston sits in ERCOT. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Houston data centers?
Across tracked campuses in Houston, Wattlas links 0 active or extended moratoria (0 total) and 19 public petitions. On physical site risk, 0 of 5 pipeline campuses sit in High or Extremely High baseline water stress (0 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Houston data center sites show active satellite land clearing?
Of 4 pinpointed pipeline sites monitored with satellite imagery in Houston, 0 (0.0%) show active earthwork or pad expansion, including 0 sites clearing ahead of a reported construction stage.