Phoenix
Phoenix is market 10 of 34: about 8.4 GW across 35 campuses in 2 counties. 3 under construction and 0 moratoria in force. Checked 28 Nov 2026
Largest campuses
All 35 campuses
The shape of the market
By stage
- Announced4
- Site permit22
- Building permit6
- Construction3
Stated and estimated
- Stated on record212 MW
- Our estimate≈8.2 GW
By county
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Phoenix in the app, free
Questions
How many data centers are in Phoenix?
42 tracked pipeline campuses (8.4 GW estimated total, 212 MW reported) across 2 counties in Arizona. Key signals: 6 sites showing earthwork in satellite imagery, 19 local petitions, 42 pipeline sites in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (212 MW) with estimates from floor area, acreage, investment or backup generation. 18.2% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
No moratorium is in force in Phoenix today. 0 moratoria and 19 petitions are on record across the market. 42 of 42 campuses sit in high water stress.
How is this market drawn?
Phoenix is the 2 counties around its campuses in Arizona, in Non-ISO. It ranks 10 of 34 markets by estimated pipeline.
How large is the Phoenix data center pipeline?
Wattlas tracks 42 upcoming pipeline campuses in Phoenix (27 verified, 3 under construction, 30 permitted), representing 212 MW in reported capacity and 8,425 MW total estimated pipeline. Projects with the largest reported figures include Tract Buckeye (1,000+ MW), Project Baccara Campus (500–999 MW), EdgeCore Mesa Campus (50–499 MW).
What are industrial power rates and serving utilities in Phoenix?
Phoenix sits in Non-ISO. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Phoenix data centers?
Across tracked campuses in Phoenix, Wattlas links 0 active or extended moratoria (0 total) and 19 public petitions. On physical site risk, 42 of 42 pipeline campuses sit in High or Extremely High baseline water stress (42 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Phoenix data center sites show active satellite land clearing?
Of 33 pinpointed pipeline sites monitored with satellite imagery in Phoenix, 6 (18.2%) show active earthwork or pad expansion, including 5 sites clearing ahead of a reported construction stage.