Richmond / Central & Southern VA
Richmond / Central & Southern VA is market 7 of 34: about 14.7 GW across 31 campuses in 18 counties. 4 under construction and 0 moratoria in force. Checked 28 Nov 2026
Largest campuses
All 31 campuses
The shape of the market
By stage
- Announced3
- Zoning8
- Site permit15
- Building permit1
- Construction4
Stated and estimated
- Stated on record1.0 GW
- Our estimate≈13.7 GW
Who is building
MicrosoftNot on record4
Amazon420 MW3
Iron Mountain200 MW2
Tract2,400 MW1- Adp Carmel Church Data Hub300 MW1
By county
- Chesterfield9
- Henrico5
- Mecklenburg5
- Louisa4
- Caroline3
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Richmond / Central & Southern VA in the app, free
Questions
How many data centers are in Richmond / Central & Southern VA?
37 tracked pipeline campuses (14.7 GW estimated total, 1,000 MW reported) across 18 counties in Virginia. Key signals: 13 sites showing earthwork in satellite imagery, 11 local petitions, 12 pipeline sites in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (1,000 MW) with estimates from floor area, acreage, investment or backup generation. 40.6% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
No moratorium is in force in Richmond / Central & Southern VA today. 0 moratoria and 11 petitions are on record across the market. 12 of 37 campuses sit in high water stress.
How is this market drawn?
Richmond / Central & Southern VA is the 18 counties around its campuses in Virginia, in PJM. It ranks 7 of 34 markets by estimated pipeline.
How large is the Richmond / Central & Southern VA data center pipeline?
Wattlas tracks 37 upcoming pipeline campuses in Richmond / Central & Southern VA (24 verified, 4 under construction, 22 permitted), representing 1,000 MW in reported capacity and 14,673 MW total estimated pipeline. Projects with the largest reported figures include North Creek Tech Campus (1,000+ MW), Tract Hanover Technology Park (1,000+ MW), EdgeCore Shannon Hill Campus (1,000+ MW).
What are industrial power rates and serving utilities in Richmond / Central & Southern VA?
Richmond / Central & Southern VA sits in PJM. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Richmond / Central & Southern VA data centers?
Across tracked campuses in Richmond / Central & Southern VA, Wattlas links 0 active or extended moratoria (0 total) and 11 public petitions. On physical site risk, 12 of 37 pipeline campuses sit in High or Extremely High baseline water stress (0 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Richmond / Central & Southern VA data center sites show active satellite land clearing?
Of 32 pinpointed pipeline sites monitored with satellite imagery in Richmond / Central & Southern VA, 13 (40.6%) show active earthwork or pad expansion, including 12 sites clearing ahead of a reported construction stage.