Northern Virginia
Northern Virginia is the largest US market: about 37.5 GW across 261 campuses in 14 counties. 30 under construction and 1 moratorium in force. Checked 28 Nov 2026
Largest campuses
All 261 campuses
The shape of the market
By stage
- Announced23
- Zoning69
- Site permit124
- Building permit15
- Construction30
Stated and estimated
- Stated on record1.4 GW
- Our estimate≈36.1 GW
Who is building
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Northern Virginia in the app, free
Questions
How many data centers are in Northern Virginia?
267 tracked pipeline campuses (37.5 GW estimated total, 1,432 MW reported) across 14 counties in Virginia. Key signals: 77 sites showing earthwork in satellite imagery, 1 active/extended moratorium, 86 pipeline sites in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (1,432 MW) with estimates from floor area, acreage, investment or backup generation. 31.6% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
1 moratorium is in force in Northern Virginia, covering 156 campuses. 1 moratorium and 25 petitions are on record across the market. 86 of 266 campuses sit in high water stress.
How is this market drawn?
Northern Virginia is the 14 counties around its campuses in Virginia, in PJM. It ranks 1 of 34 markets by estimated pipeline.
How large is the Northern Virginia data center pipeline?
Wattlas tracks 267 upcoming pipeline campuses in Northern Virginia (151 verified, 30 under construction, 140 permitted), representing 1,432 MW in reported capacity and 37,504 MW total estimated pipeline. Projects with the largest reported figures include George Washington Village Data Center (1,000+ MW), Spring Valley Technology Park (1,000+ MW), Digital Dulles Land Condo (EPLAN-2024-0060) (1,000+ MW).
What are industrial power rates and serving utilities in Northern Virginia?
Northern Virginia sits in PJM. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Northern Virginia data centers?
Across tracked campuses in Northern Virginia, Wattlas links 1 active or extended moratorium (1 total) and 25 public petitions. On physical site risk, 86 of 266 pipeline campuses sit in High or Extremely High baseline water stress (0 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Northern Virginia data center sites show active satellite land clearing?
Of 244 pinpointed pipeline sites monitored with satellite imagery in Northern Virginia, 77 (31.6%) show active earthwork or pad expansion, including 55 sites clearing ahead of a reported construction stage.