In forceMoratorium

Milton (Fulton County) moratorium

Milton (Fulton County), Georgia paused new data center approvals on 15 Jun 2026 for 30 days, citing zoning and rules. Checked 23 Nov 2026

Started 15 Jun 20265 of 7 months passedEnds 16 Jan 2027

The facts

Passed by
City Council, 15 Jun 2026
Reason
regulatory_gap
Term
Initial 30-day moratorium enacted 2026-06-15; bridged by a short housekeeping extension on 2026-07-06; extended for up to 180 days via Agenda Item 26-208 on 2026-07-20, expected to run through January 2027 unless council lifts it sooner
Legal basis
City Council resolution enacting a 30-day pause on data center applications and permits, subsequently extended
What happened next
City Council unanimously enacted a 30-day moratorium June 15, bridged it with a short extension July 6, and extended it for up to 180 days on July 20

Know when Milton (Fulton County) votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Milton (Fulton County) paused data centers?